Wendlingen hydroelectric power plant
Location
73240 Wendlingen am Neckar
Partly concealed in underground structures, the hydroelectric power plant in Wendlingen was constructed in 1990 on the publicly owned weir. It generates approx. 3.2 million kilowatt-hours of electricity p.a. Water is fed to a bevel-gear bulb turbine with a propeller diameter of approx. 2 metres at a rate of up to 20 m3 per second via a fall measuring around 3.75 metres. The generator has an installed capacity of approx. 0.5 megawatts, which is equivalent to about 700 h.p.